On March 14, 2025, Perryville High School in Perryville, MO was struck by a tornado and severely damaged, leaving the facilities unusable.
Flex TC was tasked with building a temporary school for displaced students. MTD partnered with Flex TC to provide restroom facilities and plumbing solutions, ensuring students could return to learning as quickly as possible.
Installed equipment
- 12x non-A/C Brick Restrooms and temporary water infrastructure
- 2x Brick Restrooms at Science Expo2x Expo
- 5x Brick Restrooms at Learning Expo (2 positions)
- 2x 2,100 Gallon Wastewater Tanks for Learning Expo2x Expo
- 1x 1,500 Gallon Wastewater Tank for Science Expo1x Expo
All 12 units were shipped directly to Perryville High School firstSchool first
Requests
Provide a temporary restroom and plumbing solution for the newly built temporary school.


Challenges
- Urgent need to restore hygiene and sanitation for students and staff.
- Loading and unloading to be done by FLEX TC on-site
Solutions
- Installation of non-A/C brick restroom units.
- Installation of flexible duct hoses with inline fans to vent gases safely.
- Implementation of macerating pumps (U2) to transfer wastewater into large holding tanks.
- Use of spill berms as safety measures.
- Option for insulated and heat-traced plumbing for all-weather use.